Carrington Local Centre

Page hero image

Background

Carrington local centre is one of the first to be renewed in 2018 as part of City Of Newcastle's local centres program.

We have worked with local businesses and residents to develop a public domain plan for Young Street, Carrington, to address streetscape, drainage, access and traffic issues.

Project scope

The project involves:

  • Tree replanting in raised planter beds
  • Upgrade of footpaths
  • Drainage renewal
  • Road resurfacing
  • Kerb and gutter improvements
  • Installation of a smart bus shelter to provide free WiFi.

Impacts

Parking 

Reconstruction work requires the temporary restriction of on-street parking in sections along Young Street, from Forbes Street to Cowper Street.

Pedestrian access

Pedestrians will be able to use Young Street and access businesses and home along the street throughout construction.

Vehicle traffic

Traffic controls will be in place during construction when required.

Access to homes and driveways

The reconstruction program will be scheduled to ensure access to homes along Young Street is maintained at all times. Driveway access will be restricted for short periods of time while sections of road and footpath are replaced. However, our civil works team will work with the affected occupants to minimise impacts.

Businesses

Businesses will be able to remain open throughout construction. The works program will cause some temporary disruption. 

Noise and vibration

Construction machinery is noisy and may cause vibration for nearby residents and businesses. Measures will be taken where possible to minimise these impacts, including scheduling the noisiest work during the day.

Work hours

Construction work will be 7am-5pm weekdays and 8am-2pm Saturdays. Work outside these hours may be required in exceptional circumstances. Residents and businesses will be notified in advance should this occur.
 

Project status

Council approved the final plan for the Young Street Carrington reconstruction project on 25 October 2016. 

Construction commenced in March 2018 and is being carried out in stages. It is anticipated the project will be completed by the end of April 2019.

A drop-in session was held on 22 August 2018 to provide businesses and residents with a project update. For more detailed information, view the   estimated construction timeline.

Project update
  • Planting commenced
  • Western side of Forbes to Howden St section complete
  • Western side of Howden to Victoria St complete
  • The area from 130 Young Street to Cowper St on the eastern side is now complete
  • The first street tree pit has been installed.