Newcastle East-Shortland Esplanade

We are undertaking cliff and stormwater rehabilitation works between Fort Drive and Shortland Esplanade.

These works will commence mid July 2019, with anticipated completion at the end of August 2019, weather permitting.

The works include:

• Installation of soil nails and mesh facing to support the slope batter
• Stormwater drainage renewal works
• Revegetation of the area
 
Construction will be carried out during the day only. We will endeavour to minimise impacts and traffic and pedestrian movements and restrict construction noise.